Main Factory Topped Out in 58 Days – JINRAY Sets “Development Zone Speed”Issuing time:2023-06-27 11:51 Recently, at the construction site of Zhejiang JINRAY Electronics Technology Co., Ltd.'s electronic-grade wafer and epitaxial wafer manufacturing project, the company's Vice General Manager, Gu Kaifeng, excitedly said: "From foundation construction to topping out, it took us only 58 days. We completed the topping out of the main factory (epitaxial plant) a week ahead of schedule."
‘"Due to the impact of the pandemic, there is a significant supply-demand imbalance in the semiconductor industry. We are racing against time to speed up the construction so we can start production as soon as possible and meet market demand," Gu Kaifeng told reporters. It took just six months from the start of construction to the topping out of the main factory. Especially after the completion of the pile foundation project in January of this year, the progress of the plant construction accelerated further, with new milestones achieved every week and every month. |